Despite strong community support, a Transport for NSW feasibility study of the Canberra to Port of Eden Railway has found the project is not viable because the costs are higher than the potential revenue.

The study was funded with $1 million provided by the NSW Government in 2018, and it found that the project would cost $6.3 billion to complete.

The proposed line would carry passengers and freight and would rebuild the existing line between Queanbeyan and Bombala, and build new line joining Canberra Airport in the north and Port of Eden in the south.

Member for Eden-Monaro, Kristy McBain, has commented that many people across the electorate are disappointed by the result of the feasibility study.

“People have told me they feel the report failed to fully consider the passenger and freight potential with linkages to the Port of Eden, Canberra Airport and beyond. Considering the $1 million price tag, it’s a shame that the community doesn’t appear to have confidence in the outcome,” Ms McBain said on 6th October.

The report says that despite using “optimistic” demand projections and assuming freight would be diverted from other NSW ports to the Port of Eden, the numbers are clear.

“The full project from Canberra Airport to Port of Eden only generate benefits of $225.8 million during the life of the project, compared against the cost to achieve this benefit of $5447.6 million.”

The proposed 300km railway would pass through rugged terrain and areas of significant environmental value, such as national parks, and would require extensive works, including major tunnels, bridges and viaducts, especially between Bombala and Eden and the Canberra Airport.

Bombala Railway Station.

Bombala railway station. Photo: File.

“The costs of reinstatement of the non-operational railway are significant, and the cost to construct the railway down to Port of Eden is extremely high due to the topographical challenges and the environmental constraints,” the report says.

“While the sections from Queanbeyan to Bombala to Port of Eden are expensive and difficult to achieve, they could be delivered with substantial investment.”

While the railway line was originally identified as a potential economic opportunity for the Snowy Monaro region and southwest region of NSW by engineer Edwin Michell, community feedback since the report was published in late September 2020 has pointed out that the value the rail link would provide to regional communities is not a simple matter of cost versus revenue.

“The report does not take into account the benefits of the railway to us all in reducing our use of fossil fuels and making our roads safer, as well as connecting isolated communities,” said Cooma resident Peter Mirian.

Ms McBain said she will soon be meeting with Cooma and Monaro Progress Association to get its perspective on the rail feasibility study.

“We need a new way to assess big ideas in regional areas,” she said. “The benefits often take longer to realise and are always more nuanced than in metro areas.”

“Now is the time to invest in our regions, to make the most of the learnings and opportunities presented by the challenges of 2020 and ensure we are central to the reset and renewal of the Australian economy.”

For more information, visit Transport for NSW.

Join the conversation

4
All Comments
  • All Comments
  • Website Comments
LatestOldest

Kristy McBain may feel that many people are disappointed with this result. Others are not at all surprised. This is the third or fourth investigation into the feasibility of such a link – all coming to exactly the same conclusion. Let’s just finally accept the ‘umpire’s decision’ on this occasion and move on. The $6.3 billion could be spent in this area on very much more worthwhile infrastructure projects (the obvious first one, constructing a much-needed and overdue freeway from Canberra to Bateman’s Bay to replace the appalling, antiquated Kings Highway, to include a tunnel down the escarpment – not just providing a decent road, but also significantly cutting the road toll).

Peter Lacey
President, South Coast History Society.

Allan Lehepuu7:23 am 16 Oct 20

There was a trial of a commuter bus from Cooma linking with the ACTION service at Calwell in the ACT a number of years ago.
That was abandoned due to lack of patronage.
The convenience of a car and trucks in this low population density region is just too great for rail commuting to overcome.
If there is a lazy $5.5 billion around to be spent in the region duplication of the Monaro (B23) and Snowy Hwy’s (B72) would be of greater benefit to more residents and businesses of the Monaro and the Bega Valley.

Nienke Haantjens11:44 am 10 Oct 20

What a pity, sounds like a good idea. I remember when the train went to Bombala.

My understanding is the Sydney Rail infrastructure is also NON PROFITABLE.
Rightly so, the government underpins the cost overrun to support the Sydney/Australian economy.

The government should also underpin the cost overrun to the same level for modern rail infrastructure development from Canberra/Queanbeyan to Port of Eden.

Kirsty this is not an unreasonable request of the Government.