Briars Sharrow Road during a flood in 2021. Photo: Ashley Warwick.
Hopes of accelerating a months-long bridge closure are in doubt as wet weather slows works on the project.
Earlier this year Queanbeyan-Palerang Regional Council (QPRC) temporarily closed Briars Sharrow Bridge to allow the building of a higher replacement bridge.
The new bridge will replace the existing causeway, which can flood in heavy rains.
But wet weather has hampered its progress, leaving QPRC unable to pull the trigger on a $300,000 plan to accelerate work to finish it ahead of schedule (with the money to only be spent if the acceleration could occur).
In the latest project announcement, the council said its attempt to speed up the works was in doubt.
“Unfortunately, the frequent wet weather and unsuitable ground conditions experienced over the last six to eight weeks did slow progress on the earthworks,” its statement revealed.
“While earthworks have progressed, we have not been able to accelerate the works in this phase as we had hoped due to the wet weather. With wet weather affecting the ability to accelerate the earthworks, we are working with the contractor to accelerate other aspects of the program, by considering alternative construction methods, staging of pavement upgrades and other matters.”
When contacted for comment by Region, a council spokesperson said the realisation was made “in recent days”.
“We are focused on completing the project as quickly as possible, including considering accelerating aspects of the program,” they said.
Resident Ashley Meyer-Dilley told Region she was sceptical about the claims of works being rained out.
“The wet weather excuse I find hard to believe, to be honest – we’ve had one of the driest winters on record,” she said.
“I’m not really sure where this wet weather excuse is coming from, while the ongoing closure of Foxlow Bridge means another key route remains out of action.
“I appreciate that there’s always unforeseen circumstances, but it goes back to council’s lack of communication and consultation with the community.”
Since the bridge closure, Ms Meyer-Dilley has carpooled to work with her partner and says she has cut down on weekend adventures.
She also noted the end of the fuel excise cut had only increased the cost of petrol.
“I don’t go out and socialise with my friends at the moment because the travel is too much [of a cost],” she said.
“I’ve got horses. I’d love to go out and ride and compete and do those things.
“I’m sacrificing those things … to cover the extra fuel bill to get to town for work.”
She flagged the need for a discussion of support for affected Hoskingtown residents.
“I appreciate you can’t ask council for a handout … [To] have them not come to the table and help us in other ways, like rates, is really disappointing.”
According to QPRC, efforts to build the bridge at Briars Sharrow are expected to be finished in March 2027.
The council spokesperson said that despite the rain, the project was moving ahead.
“Earthworks are continuing, and the project will soon progress to the piling works for the new bridge,” they outlined.
All 35 planks for the bridge have been poured off-site, with piling works for the bridge expected to start later this month.
Briars Sharrow Road remains closed as work to build a replacement bridge continues. You can find more information about the project on the council’s website.