Several investigations are already underway into the delayed pool upgrades in the Monaro region. Photo: Google Earth.
A fresh attempt to launch an independent investigation into delayed council pool upgrades in the Monaro region has been knocked back.
Snowy Monaro Regional Council (SMRC) had been upgrading the Cooma and Bombala public pools, but in late April cancelled the main upgrade contract with Dalski Pty Ltd amid claims that subcontractors for the project weren’t being paid.
The following month, the company went into administration, with SMRC approving more than $500,000 in works to wrap up the projects.
Councillor Reuben Rose led the push for an independent investigation into what happened.
He said SMRC needed to understand how the earlier stages of the project unfolded, focusing on aspects such as its timeline and financial management.
“We faced a range of escalating costs, which probably could be as much as $2 million, that were unplanned,” Cr Rose said.
“It’s very clear that this is one of the most significant and serious capital project failures in the council’s recent history. Staff, I think, have done a terrific job in trying to mitigate some of the problems.
“But as a governing body, I think we have a duty to understand how this all happened.”
Cr Rose pointed to about 25 subcontractors who had allegedly been owed about $500,000, while the council has also lodged a $3.3 million claim with the administrator.
“This is not to point the finger at any particular staff members,” he said.
“There’s no sense of that. What we need to do, from a governance point of view, is to say, ‘What has been wrong in this whole process since it was conceived in 2018?'”
Council documents reveal an investigation could cost up to $130,000.
Staff also noted that SMRC’s internal audit process is considering the projects, while the controversial upgrades have also been referred to the NSW Audit Office for a potential investigation.
But it’s a cost that Cr Rose believes would be worthwhile.
“[Those two processes] aren’t going to get to the bottom of this because they’re not going to be able to commission the sort of independent investigation that is needed,” he told the meeting.
He also said that five months after the council agreed to meet with the audit committee, no such encounter had been arranged.

The Bombala and Cooma pools have been closed for months. Photo: Bombala Swimming Pool/Facebook.
Cr Tricia Hopkins said those other bodies were better placed to carry out an audit and any future investigation by SMRC could dig into the “gaps” in those reports.
While she supported investigating the project, she said the “timing is not right” for the council to launch a new investigation.
“I personally would like to see a report that does address what went wrong … But I think there are two independent audits that are underway or likely to be underway soon.”
Cr Lynda Summers said the council should consider its own audit in the future.
“It will be, I think, more useful to use those outcomes [of other audits] to frame any further investigation, should there be questions that we still have,” she said.
“I think that in the course of time, this is going to be a standard failure of a business that did not manage itself well.”
The meeting heard that both the Cooma and Bombala pools are unlikely to open before 2027.
However, SMRC has been offering free admission to the pools at Adaminaby and Berridale until they reopen.