Eurobodalla Shire Council’s planning department seems likely to approve this week a development application for a large house and garage on Wagonga Inlet foreshore that seemingly fails several provisions of the Narooma Township Development Control Plan (DCP).
In early April council staff issued a formal request for further information on development application (DA) 0339/26, identifying DCP variations including garage site coverage and foreshore setbacks.
On 13 October, council performed a view-sharing and height-pole inspection at the neighbouring property, 18 Gina Court, which is owned by Julian Poulter. He showed planners several aspects of the DA that do not comply with the Narooma Township Development Control Plan (DCP).
The areas of non-compliance include its scale, such as its 38.55 m width. Mr Poulter said that was wider than the Narooma Sports Centre and would become the largest building on Narooma’s foreshore.
At 161 square metres, the 4.69 m high proposed garage exceeds the DCP’s 60 square metre limit and is larger than a neighbouring property.
“Who needs a garage capable of storing 12 cars,” Mr Poulter said. “I’m all for development, but this is unnecessarily large and completely blocks our natural light and views.”

AI-generated image of the existing view of Wagonga Inlet foreshore and the view with the proposed dual occupancy building. Photo: Supplied.
Mr Poulter has requested that the DA be referred to councillors plus a notice of motion to raise awareness of how council uses its own planning instruments.
“If this DA goes through then the Narooma DCP will be worthless,” he said. “Approval would see Narooma foreshore turned into a concrete jungle yet the DA obviously fails the DCP.”
On 30 October, Gary Bruce, council’s director planning, housing and environment, wrote to Mr Poulter in response to letters he had written to council’s general manager and councillors in September and October.
“The amended plans have been further assessed by council officers and are now deemed satisfactory with regard to the DCP, including the principles of view sharing and the identified variations,” Mr Bruce said. “The assessment of DA0339/26 is now being finalised and is anticipated to be determined by Friday 6 November 2026 as approved under delegated authority by council’s division manager, development services.”
Mr Poulter said he had raised legitimate concerns with the council and Member for Bega Dr Michael Holland about how the various planning regulations were being used. “Now it seems Mr Bruce is in a hurry to approve the DA before those questions can be addressed,” Mr Poulter said. “The community should be concerned.
“Without a deferral and appropriate councillor scrutiny, the Narooma community risks being denied the opportunity to see its elected representatives defend the very planning instruments its council previously adopted,” he said.
“I believe Mr Bruce’s letter raises significant questions about the effectiveness of Narooma’s planning controls, particularly given the exceptional scale of the proposed development and the specific provisions of the DCP that appear to conflict with its design.”

The peak of the proposed development is more than halfway up the upper floor of a neighbouring property. Photo: Eurobodalla Shire Council.
He also questioned why the DA would be determined so quickly after the amended drawings were received.
“The applicant was granted months of extra time to respond to council’s notice of variations and now we are given just a few days to respond. The whole DA process seems to be broken.”
Mr Poulter said the likely approval of a seemingly non-compliant DA was in the context of the new planning regime effective 1 September where councils no longer must notify neighbours or publicly exhibit DAs for dual occupancy, attached dwellings, dwelling houses, multi-dwelling housing, and subdivisions.
“Not only will residents be unaware of a DA until the bulldozers arrive next door, but also the DAs may be non-compliant,” he said. “People need to understand why this is such a dangerous precedent that will impact them directly.”
Furthermore, if a submission is lodged for any of those excluded types of development it is not considered a formal submission and need not be considered during the DA’s assessment.
On 8 September, the council’s acting assessment manager Katrena Fuller told councillors that was why it was very important that the council had strong and robust DCPs and policies that clearly defined what the council would and would not accept.
“This is the first indication that under the new regulations, council’s planning department will throw DCPs into the bin and neither the community nor councillors will have any influence on development,” Mr Poulter said.
Region asked the council why the planning department now deemed the DA satisfactory with regard to the DCP.
In a statement, a council spokesperson said the DA for a dual occupancy at 20 Gina Court was still under assessment.
“The application has been notified on two occasions following modification of the proposal by the applicant,” the statement said.
“The applicant has made a series of changes to the proposal to address council policy and concerns raised by neighbours.
“All development proposals are assessed on merit and in accordance with council policy.
“Once the assessment is finalised, the application will be determined in accordance with council procedure.”