The proposed operation would be to the west of the existing Gunlake Quarry, in southern NSW. Photo: Gunlake Quarry.
The NSW Southern Highlands could become host to a new quarry extracting hard rock products for concrete, according to newly released plans.
Documents on exhibition with the NSW Planning Portal state that if approved, the so-called Carrick Quarry would produce up to 1 million tonnes per year of hard rock products.
“The rock will be won by conventional drill and blast techniques with in-pit crushing prior to loading and hauling to a separate processing area,” an environmental impact statement outlined.
“Further crushing and screening will occur in the processing area prior to transport off-site by road registered trucks for delivery to markets.”
The report also estimates the quarry would bring about 70 jobs to the region once operational.
According to the report, the site has been largely cleared, though some vegetation clearing would be needed.
The quarry is proposed for a 90.4-hectare property, which is part of the ‘Lockyersleigh’ estate. The land has been leased to Regional Group Australia Pty Ltd for the project.
It’s expected to trigger a “nett increase” in visual impact from nearby sites.
“It is well shielded by existing topography which limits views from public roads … With limited nearby residential receptors, it is considered the project is well suited for development as an extractive operation.”
The site, about 5.5 kilometres north-west of Maralun, was chosen because of the type of rock in the area (a mix of volcanic rocks, such as ignimbrite).
“There are limited areas where suitable resources have been identified that can sustain long-term production of the consistent high-quality aggregates demanded by the construction industry. … The Marulan district was chosen as it represents a source of suitable quality rock which is close to and would meet the requirements of existing and future markets.”
Barralier ignimbrite is described as the “target resource”.
About 36 blast events are predicted each year, during the proposed 30-year life of the quarry, while a noise assessment found that “only negligible additional impacts” were expected during the quarry’s operation.

A map showing the layout of the proposed Carrick Quarry. Image: Supplied.
The environmental assessment notes that construction traffic is expected to peak at 92 daily vehicle trips (specifically around the seventh month of construction).
Once the proposed quarry opens, operational traffic is expected to peak at around 190 heavy vehicle movements each day.
“Dedicated traffic routes have been identified via Carrick Road, Brayton Road, and Ambrose Road/Red Hills Road to the Hume Highway,” the report states.
To cope with this traffic, nearby roads and their intersections would be upgraded.
Carrick Road, currently a narrow unsealed gravel road, would be fully reconstructed, while nearby Brayton Road would also be widened to accommodate two 3.5 metre carriageways as part of the works.
It has been designed as a state significant development, meaning the planning panel will assess it before making a decision.
The proposal was initially put forward by Illawarra-based Cleary Bros (Bombo) Pty Ltd, as part of an expansion.
It was eventually purchased by Maas Group Holdings Pty Ltd, with the quarry project being developed by subsidiary Regional Group Australia Pty Ltd.
The proposal is on exhibition through the NSW Planning Panel website until 4 November.