Batemans Bay Masterplan concept plan showing land zones (MU1 mixed use, R3 medium-density residential) and maximum heights (red 50 m, gold 27 m, yellow 14 m). Photos: Eurobodalla Shire Council.
Eurobodalla Shire councillors backed away from endorsing the height controls that council staff are using to finish drafting the revised Batemans Bay Masterplan.
After almost two hours of debate they backed a motion to note the indicative building height controls, without determining their suitability or endorsing them as final development controls. They also noted the height controls were indicative for specific properties and that the masterplan study area had been reduced to exclude land east of Joes Creek (Batehaven) and the industrial area.
The height controls discussed were 14 metres (about four storeys), 27 metres (around eight storeys) and 50 metres (about 15 storeys).
However as an incentive for affordable housing to be built, a State Environmental Planning Policy (SEPP) allows buildings to be built up to 30 per cent higher than the height controls if at least 10 per cent of the floor space is used for affordable housing. That potentially allows buildings with a 50-metre height control to be built to 65 metres. SEPPs override councils’ local environmental plans (LEPs).
The council’s director of planning, housing and environment Gary Bruce said they had consulted with the community, builders, developers, business owners and real estate agents about three scenarios: higher density dwelling throughout the study area, higher density dwelling outside town but nearby, and densification of the town centre.
There was general agreement higher density dwelling outside town but nearby would see people driving their cars into the town centre, increasing traffic and demand for parking. “There was more of a desire to see things in the town,” he said.
Mr Bruce said the masterplan’s three objectives were activating Batemans Bay town centre, increasing housing diversity and promoting a climate-resilient town centre.
He said staff were grappling with the lower building heights that the community said were acceptable, the higher heights that developers said were needed to be financially feasible, and the geotechnical and flooding constraints of Batemans Bay.
“We are seeking guidance on some heights,” Mr Bruce said. “If you are against 50-metre height controls I would rather know now.”

Batemans Bay Masterplan revised concept plan.
According to the papers for the council meeting, a survey of the area’s builders found that buildings less than eight storeys (around 27 metres) in the study area and less than 12 storeys (42 to 45 metres) in the town centre likely are not financially feasible due to rising construction costs, financing issues and the need for aboveground parking because flooding rules out underground parking.
Explaining the costs to councillors, Mr Bruce said construction costs had risen 51 per cent since COVID, concrete in Eurobodalla cost double what it did in Canberra, and the shire did not have tradespeople with the skills needed for taller buildings so tradespeople would have to come from elsewhere. Additionally, the Building Code of Australia also specified certain fire safety requirements beyond 25 metres which “significantly” increased the cost of construction.
“Nothing will happen in the town centre without 50 metres,” he said.
The 50-metre buildings would be constrained to the town centre and the community has made it clear the foreshore should not be overshadowed.
Mr Bruce said the SEPP only provided for affordable housing for the first 15 years. After that developers could do what they liked.
Councillor Mick Johnson asked if that meant in 15 years’ time Batemans Bay town centre would have 65-metre towers and no affordable housing. Mr Bruce said some councils were losing their affordable housing in one go because it was all built at the same time 15 years ago.
Councillor Amber Schutz said some areas of Batemans Bay already allowed 18.5-metre buildings, which if they incorporated affordable housing, would take developers close to 25 metres, but they had not done anything with it.
“Those controls have been in place since 2012,” Mr Bruce said. “There have been maybe 10 or 15 developments, mostly on Beach Road, but not residential. The current controls aren’t working. How can we tweak them so that developers want to build?”
The motion was passed, with councillors Anthony Mayne, Colleen Turner and Sharon Winslade opposing it.
According to the council meeting’s papers, the proposed approach would require up to 2 metres of road raising over the next 75 years. The road raising would not likely occur in the lifetime of the masterplan given growth in the area is slow.
The new concept plan would realise 6254 additional dwellings compared with Eurobodalla’s current LEP, more than there is a market for currently, but it creates diversity of housing options by providing for townhouses, low-rise flats, medium density and higher density in a variety of locations.