A map of the proposed development. Image: Brightway Development Group.
Eurobodalla Shire councillors have deferred deciding on whether a controversial rezoning proposal in Broulee should proceed to the Minister for Planning, Housing and Infrastructure for a Gateway Determination and requested a supplementary report from staff within 90 days.
The shire desperately needs housing, particularly affordable and smaller dwellings. The planning proposal comes with promises of many community benefits through a Voluntary Planning Agreement (VPA) including 140 affordable, build-to-rent and key worker homes, and contributions to the costly necessary upgrade to the Tomakin Sewerage Treatment Plant. Some dwellings would be kit-style, likely delivering housing faster than by conventional building.
However, the proposal does not comply with council’s planning framework, would set a precedent for other developers, and potentially see the village’s population rise from 1947 to 3454.
The developer, Brightway Development Group, cited the July 2026 change in state legislation that permits proposals that respond to significant changes, such as demographic changes, that have not been recognised in the existing planning framework.
The planning proposal for 207 Broulee Road covers 125 hectares of land zoned RU1 – Agricultural Production and C2 Environmental Conservation. It seeks to rezone 62.14 ha of the RU1 land to R2 low density residential and expand the C2 zone to 30.82 ha. The R2 zoning would enable 293 dwellings on compact housing lots, 331 on standard housing lots, plus 61 other residential lots – totalling 685.
The developer’s previous planning proposal for 800 lots was refused by council and the Southern Regional Planning Panel in 2024.
Councillors wanted to understand what had changed from 2024 to make staff recommend the revised planning proposal, plus answers to the questions raised by community members in the public forum before the council meeting held this week.
The community and councillors also struggled with the process whereby the proposal goes for the Gateway Determination with only preliminary information on bushfire evacuation, road access, water and sewer infrastructure, flooding, wetlands, biodiversity and heritage. The detailed reports and community consultation follow the Gateway Determination.

The 125.3 hectare site in Broulee. Photo: Brightway Development Group.
In the public forum session nine people spoke against the proposal and six people spoke in its favour, plus Brightway Development Group CEO Ed Fernon.
The six people included someone speaking on behalf of struggling young families, a long-term renter and a long-time resident who had seen a lot of change. “The question is always do we plan for it well,” she said, adding there were no affordable options for older people who need to downsize.
Another speaker said half of renters were under rental stress, with more than 30 per cent of their income spent on rent. Some said the proposal would create a community, not just housing, that the housing was needed now and for future generations, and that thoughtful, considered development could protect what the community loves about the area.
Mr Fernon said the planning proposal was needed because there was a huge need for smaller homes, that the [6254] additional dwellings outlined in the current draft Batemans Bay Masterplan would not be delivered for many years, that most of the zoned land in Broulee had environmental constraints, and that analysis he commissioned showed council faced a 2258 shortfall of housing lots in the shire compared with its predictions.
Speakers against the planning proposal said it was expensive land, an expensive development with the land unconnected to services, and isolated from employment, shops and services, so not suitable for affordable housing. Others said there was only one road in and out to the flood and bushfire prone area, and that there was enough zoned land for housing in the shire and in Broulee.
Some said that type of development should be in Moruya where the NSW Government is contributing funding, that affordable housing should be in Eurobodalla’s three main town centres, that it ignored all council’s planning regulation and risked council’s reputation with developers who had complied with its regulation.
Others said the proposal was little changed from the 2024 one, and that preliminary comments from government agencies indicated it had not addressed the issues that were raised back then, there was no guarantee that the housing would be delivered, it placed too much pressure on already strained sewerage infrastructure, the extent of the land shortage had not been verified, there was too much reliance on the VPA, and that there was incomplete information for a proposal of its scale and nature.
Councillors agreed and unanimously passed a motion for a supplementary report including written confirmation from the NSW Government about the applicable strategic merit assessment framework.