The Australian Energy Regulator (AER) has determined TransGrid failed to consider all credible options for its HumeLink project, in what is considered a big victory for landowners opposed to powerlines running through private land as per original plans. This development is significant because failure to consider all credible options is a breach of the requirements … Continue reading Energy regulator determines TransGrid didn’t consider all credible routes for HumeLink project