Eco constraints set the pace for Merimbula boardwalk replacement

| By Denise Dion
Join the conversation
1
Two women stand on an old jetty that is part of the old merimbula boardwalk that is about to be replaced in 2026.

Planning and projects coordinator Amelia Baum, left, and project manager Jess Crawford at Merimbula boardwalk, close to Market Street, prior to its demolition. Photo: Denise Dion.

Years of planning, environmental assessment, design and approvals are coming to fruition as the much-loved Merimbula boardwalk undergoes replacement. Despite its relatively short 1.7 km length, progress is slow as demolition and building is taking place on an environmentally sensitive site.

Bega Valley Shire’s project manager Jess Crawford said it was adjacent to oyster leases, seagrass beds, mangroves, saltmarsh, mapped coastal wetlands and existing sewer infrastructure.

“This is a very environmentally constrained site which required a lot of background work. We did aquatic studies on the saltmarsh, seagrass and threatened plant communities and a detailed design on how to demolish and reconstruct the boardwalk,” Ms Crawford said.

To minimise impacts, Wagners – chosen for their prior experience in environmentally sensitive areas – can only work within a 4 m corridor, just 2 m either side of the centre line of the existing boardwalk. At the Lakewood Drive end of the boardwalk, bog mats were put down to spread the machinery load. Buckets and mats were put down to capture sawdust as the existing timber piles were cut as low as possible.

READ ALSO Merimbula Boardwalk closures flagged as start of $14 million upgrade looms

In the central and most environmentally sensitive section of the boardwalk, demolition is by hand. In this section, Wagners will be pile driving from newly completed sections of boardwalk to provide the substructure for the next section.

The contractor is further constrained as piling can only take place two hours either side of low tide and not all low tides come within the approved work hours for the project. Pile driving comes with its own issues due to the varying ground conditions.

“Where there’s rock we can connect directly with shorter piles but where there’s mangrove mud we need to hit a certain level of resistance for the piles to be stable for the life of the boardwalk,” Ms Crawford said.

In the third and final section of the boardwalk, which joins Market Street, demolition and construction will be supported by a barge.

Planning and projects coordinator Amelia Baum was closely involved in the community consultation when a replacement was first discussed. She said the new boardwalk, 2.5 m wide (the current boardwalk is 1.5 m) would be accessible for prams and wheelchairs but not bikes.

“There was a majority view that people wanted it as much like the existing boardwalk as possible,” Ms Baum said.

That means the new boardwalk will be open but with a timber kick rail either side for safety. Seating, any top rails and jetties will be timber as well, Ms Baum said.

Fisheries wanted to minimise shading beneath a widened boardwalk and BVSC wanted a structure with a minimum 50-year design life. A widened solid deck would have increased shading and fibre reinforced polymer (FRP) was suggested by Wagners as the FRP mesh decking allows light penetration. Wagners said FRP had a 100-year design life and all components were coated with a UV-resistant layer which had undergone the equivalent of 125 years of accelerated weathering for UVB and moisture.

READ ALSO 'Exciting step forward' as contract locked in for Merimbula Boardwalk upgrade

“Once a long-life deck was selected, it made sense to have a structural system with a similar design life rather than a substructure that may require replacement much earlier,” Ms Crawford said.

There will be new entrances at both ends of the boardwalk and at the Market Street end the boardwalk will flow over the last section of rock to join a recreation area before rising up to street level.

There’s hope the boardwalk can be finished in time for Christmas, despite its original finishing date being in 2027, but like all outdoor works it is weather dependent and relies on the patience and understanding of local residents. Recently a chainsaw was used to cut through vegetation to allow someone access to the water.

“Unauthorised access is one of our biggest issues. People have moved barricades, entered construction zones, the site compound and accessed the site via the water. People are walking through sensitive foreshore habitat, the very areas we’re working so hard to protect,” Ms Crawford said.

“We ask them to be patient. It’s for their safety and for the protection of the environment,” Ms Baum said.

The boardwalk replacement has $10 million in funding from state and federal sources.

Free, trusted local news delivered direct to your inbox.

Keep up-to-date with what's happening around the Capital region by signing up for our free daily newsletter.
Loading
By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.

Join the conversation

1
All Comments
  • All Comments
  • Website Comments
LatestOldest

Weather has been great so can’t use that an excuse. The utterly hopeless Council minions, a mismanaged project, massive overruns and budget blow outs. Watch out for sea grass! Welcome to Bega Valley Shire Council.