Eurobodalla Council is upgrading sewerage plants at Batemans Bay (pictured) and Tomakin. Photo: Eurobodalla Shire Council.
A southern NSW council has voted to push ahead with a $62 million infrastructure upgrade.
Eurobodalla Shire Council has been planning a Tomakin Sewerage Treatment Plant (STP) upgrade for several years. This, along with works to the Batemans Bay plant, is being driven by population increases and climate-fuelled peak wet-weather flows.
In council meeting papers, a motion calling for the project to move ahead initially included a point that doing nothing was “not an option”.
But councillors instead voted to simply acknowledge the “necessity” of the project while moving it to the next stage, in which tender documents will be prepared and statutory approvals sought.
According to the business case for the upgrades, the multimillion-dollar project would expand Tomakin’s plant, more than doubling its treatment capacity.
The plan involves “targeted upgrades” to extend the use of existing assets, changes to sludge-handling processes, improved environmental performance and other infrastructure upgrades.
As part of the overall project, the plant will take on flows from the Malua Bay and Lilli Pilli catchments, increasing its average dry-weather flows by about 500 kilolitres a day and reducing pressure on the Batemans Bay facility.
“These loads cannot be accommodated within the existing plant configuration,” the document notes.
“The timing and scale of the Tomakin STP upgrade is directly linked to the performance of Batemans Bay STP, which is also stressed under concurrent peak loading and wet weather event.”
A recent councillor briefing heard that the estimated project cost was now $62 million (or $34.6 million higher than the current budget).
Infrastructure services director Graham Attenborough said the COVID-19 pandemic, the Ukrainian War and the Southern Water Supply Storage project were driving the planned upgrades’ rising capital costs.
“We’re wanting to make sure that we’re on the right track,” he said.
“We’re wanting to take councillors on the journey before we turn up and go, ‘Hey, can you give us $62 million to build this thing?’.”
He said extra borrowings would be needed to cover that cost.
Mr Attenborough added that the prospect was “always envisioned”, and that a 3.5 per cent increase in water rates would take place over a three-year period.
During the meeting, Cr Sharon Winslade expressed concern over the price tag.
“Obviously we need to do it — there’s no two ways about that. But it’s a hairy, scary budget,” she said.
Cr Winslade said councillors had been given limited information on how the loan would impact the council’s bottom line (and residents).
“This is a bit piecemeal,” she said. ”We’ve got some information in a workshop, and then other information in an agenda item.
“I’d just like us to pull it together a bit more comprehensively. We need to understand context, rationale, budget, how we’re going to pay for it, [and] how we’re going to communicate this to the community.”
During discussion, Mr Attenborough said he would need to seek further information to ensure planning for the upgrades was in line with NSW Environment Protection Authority (EPA) guidelines.
“I’m more than happy to come back to you with that question,” he told councillors.
“The EPA are a challenging regulator in terms of they change it [regulations] and then say, ‘Right, now you should be starting to comply with it and play catch-up’.”
According to meeting documents, design work on the Tomkain plant upgrades is about 75 per cent complete.
On the current timeline, construction is expected to start in late 2027 and take two years to complete.