13 August 2026

'All talk': Community advocates slam lack of action on Barton Highway duplication

| By Claire Sams
Join the conversation
1
Highway sign showing distances to Murrumbateman and Canberra

Murrumbateman’s Stephanie Helm says the delay in finishing the Barton Highway duplication project is limiting tourism to the town. Photo: File.

Amid a timeline blowout stemming from “unforeseen consequences”, Murrumbateman community advocates fear the next stage of the Barton Highway duplication is stuck spinning its wheels.

During its late-July council meeting, Yass Valley Council unanimously endorsed the list of priority projects ahead of the 2027 state election.

But the item that topped the list wasn’t something new: the Barton Highway duplication.

The highway crosses the NSW-ACT border and is a major thoroughfare for commuters, other motorists and long-range freight travelling around southern NSW.

Stage one of the duplication project was completed in 2024 ahead of a planned second stage extending it towards Murrumbateman.

There have been calls to accelerate work on the second stage, with community groups repeatedly urging governments to commit more funding and even holding a public rally in 2025.

Business owner Stephanie Helm is blunt in her assessment of where the project stands.

“It’s a lot of talk and no action, is what I’d say,” she told Region when asked about the project’s timeline.

READ ALSO Griffith man to be sentenced after his winery altered invoices to claim millions in GST refunds

The long-awaited news of money for construction has left her sceptical the next stage will be finished anytime soon.

“I think the community will keep pushing as long as we have to. We are just getting worn down,” she said.

“Every time there’s another fatality or accident, it just feels like we’ve been telling people and no-one is listening … It seems every election we have this discussion, but nothing concrete comes out of it.”

For Ms Helm, ongoing safety concerns have left her afraid for her children using the road, while she also feels the risks are limiting tourism to the town and making visitors wary of using it.

“It’s just comments that get made from customers visiting the winery,” she said.

“A lot of them have come out from Sydney [using] the Federal Highway, so they’re confused that quite a major highway is single-lane.”

In a 2019 NRMA survey, the Barton Highway was voted the worst road for congestion and safety in the Canberra/Goulburn region.

Ms Helm said the Murrumbateman bypass would be the town’s next major infrastructure project, which the council also put its support behind.

“If that bypass starts getting planned, we can start working on that safety issue for the town and start planning on how we’re going to make the best use of our public facilities,” she said.

The need for the project to help manage the town’s growth was echoed by Murrumbateman Community Association (MCA) vice-president Rowan Geddes.

He said the “no-brainer” duplication would take vehicles off roads used by locals, with both projects ideally built in “one go”.

“How much do the community and council need to lobby the government to do this work? … We’ve had stage one, which was awesome.

“Where’s the implementation plan, rather than constantly talking about it?”

READ ALSO Tip-off leads to coastal aged care provider repaying nearly $120,000 to migrant workers

When Region contacted Transport for NSW (TfNSW) for comment, a spokesperson admitted there’d been “unforeseen delays”.

They said this was due to further environmental and cultural investigations that identified areas the new road should avoid.

“While construction of the southern permanent tie-in and stage two of the Barton Highway upgrade was expected to start in 2026, this was subject to completion of the Review of Environmental Factors (REF), detailed design, property acquisitions, the construction tender process and funding considerations.”

The spokesperson also confirmed this meant the release of the REF document had been pushed back to 2027.

“TfNSW is finalising the scope and construction area for stage two within the approved budget, balancing engineering requirements, safety improvements and environmental considerations,” they said.

The next state election will be in March 2027.

Free, trusted local news delivered direct to your inbox.

Keep up-to-date with what's happening around the Capital region by signing up for our free daily newsletter.
Loading
By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.

Join the conversation

1
All Comments
  • All Comments
  • Website Comments
LatestOldest
cannedbeeria12:20 pm 12 Aug 26

Good to see that Stephanie Helm is in favour of the Murrumbateman bypass too.
She can obviously see that the old fashioned thinking that all traffic should go down the main street is outdated and dangerous.
These days small townships thrive once a bypass is completed.
Mogo? Bungendoor? Braidwood?
I can think of more.